Designer: Victor Latavish Architect 

Construction Contractor: DEC Contracting Group

Project Manager: Claude Nesbitt

Project Budget: $1,200,000

Estimated Construction Cost: $1,100,000

Building Square Footage: 52,000

Design Start Date: November 2016

Construction Start Date: August 2018

Anticipated Construction Completion Date:  January 2019