53010 CCSO CID Roof and HVAC Improvements

Print
Press Enter to show all options, press Tab go to next option

Designer: BSSW

Construction Contractor: Cedar Electro-Mechanical Inc

Project Manager: Claude Nesbitt

Project Budget:  $2,416,632

Estimated Construction Cost:  $2,055,000

Building Square Footage:  34,541

Design Start Date:  November 2016

Construction Start Date:  August 2018

Anticipated Construction Completion Date:  March 2019

Photos: 

Roof top air handlersRoof ChillerRoof