 Designer: BSSW Architects. Inc. 

Construction Contractor: TBD

Project Manager: Tony Barone 

Project Budget: $2,000,000

Estimated Construction Cost: $1,800,000

Building Square Footage: 5,300 

Design Start Date: June 2018

Construction Start Date: May 2019

Anticipated Construction Completion Date: February 2020